| United States. Court of Claims, Audrey Bernhardt - 1968 - 922 pages
...clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change : Provided, however, That the Contracting Officer,...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| 1999 - 572 pages
...Contractor of the notification of change: Provided, however, That the Contracting Officer, if he/she decides that the facts justify such action, may receive...adjustment, the Contracting Officer shall have the fight to prescribe the manner of disposition of such property. Failure to agree to any adjustment shall... | |
| 1979 - 520 pages
...clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change. Provided, however. That the Contracting Officer,...Where the cost of property made obsolete or excess as result of a change is included in the Contractor's claim for adjustment, the Contracting Officer shall... | |
| 1982 - 536 pages
...days from the date of receipt by the Contractor of the notification of change: Provided, fiou-rrrr. That the Contracting Officer, if he decides that the...payment under this contract. Where the cost of property mad» obsolete or excess as a result of a change is included in the Contractor's claim for adjustment,... | |
| 1984 - 232 pages
...clause must be asserted within 30 days from the date of receipt by the contractor of the notification of change; provided, however, that the Contracting Officer,...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| 1976 - 580 pages
...asserted within 30 calendar days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer,...asserted at any time prior to final payment under the contract. Failure to agree to any adjustment shall be considered a dispute concerning a question... | |
| 1971 - 850 pages
...be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change: Provided, however. That the Contracting Officer,...asserted at any time prior to final payment under thla contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact... | |
| 1980 - 976 pages
...sixty (6O) days from the date of receipt by the Contractor of the notification of change: prov 1 ded . however . that the Contracting Officer. If he decides...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| 1976 - 1202 pages
...days from the date of receipt by the Contractor of the notification of change; provided, however, thai the Contracting Officer, if he decides that the facts...any time prior to final payment under this contract. Failure to 7^104.1 ARMED SERVICES PROCUREMENT REGULATION CONTRACT CLAUSES AND SOLICITATION PROVISIONS... | |
| 1977 - 944 pages
...asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change; Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to flnal payment under this contract. Failure to agree to any adjustment shall be a dispute concerning... | |
| |