" If the Contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such... "
Cases Decided in the Court of Claims of the United States - Page 678
by United States. Court of Claims - 1945
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 8

United States. General Accounting Office - 1929 - 804 pages
...liquidated damages accrued to the United States. The contract provided : ABTIOLE 9. Delays — Damages. — If the contractor refuses or fails to prosecute the...or any separable part thereof, with such diligence ns will insure its completion within the time specified in article 1, or any extension thereof, or...
Full view - About this book

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - 1930 - 132 pages
...work at all times during progress, with authority to act for him. ARTICLE 9. Delays — Damages. — If the contractor refuses or fails to prosecute the...will insure its completion within the time specified in Article 1, or any extension thereof, or fails to complete said work within such time, the Government...
Full view - About this book

The Construction of Hoover Dam: Preliminary Investigations, Design of Dam ...

United States. Department of the Interior, Ray Lyman Wilbur, Elwood Mead - 1933 - 338 pages
...the work at all times during progress, with authority to act for him. ART. 9. Delays — Damages. — If the contractor refuses or fails to prosecute the...will insure its completion within the time specified in article 1, or any extension thereof, or fails to complete said work within such time, the Government...
Full view - About this book

Orders and Regulations, Corps of Engineers, U.S. Army, 1934

United States. Army. Corps of Engineers - 1934 - 396 pages
...progress, with authority to act for him. ARTICLE 9. Delays-Damages . (a) Termination for Default. — If the contractor refuses or fails to prosecute the work, or any separable part 191 7113.89 CHANGE 13, 1 Mar 50 To Part I, Chapter VII thereof, with such diligence as will insure...
Full view - About this book

Taking the Profits Out of War: Hearings Before the Committee on Military ...

United States. Congress. House. Committee on Military Affairs - 1935 - 812 pages
...work :it all times durin:; progress, with authority to act for him. ARTICLE 1. Dclau* — Dnmape*. — If the contractor refuses or fails to prosecute the...will insure its completion within the time specified in article 1, or any extension thereof, or fails to complete said work within such time, the Government...
Full view - About this book

The Code of Federal Regulations of the United States of America ..., Book 2

1939 - 1306 pages
...on the work at all times during progress, with authority to act for him. ART. 9. Delays — damages. If the contractor refuses or fails to prosecute the...will Insure its completion within the time specified in article 1, or any extension thereof, or falls to complete said work within such time, the Government...
Full view - About this book

United States Reports: Cases Adjudged in the Supreme Court, Volume 322

United States. Supreme Court - 1945 - 864 pages
...See H. Rep. No. 1794, p. 8 (57th Cong., 1st Bess.) ; 35 Cong. Rec. 4935. 8 "Delays — Damages. — If the contractor refuses or fails to prosecute the...will insure its completion within the time specified in Article 1, or any extension thereof, or fails to complete said work within such time, the Government...
Full view - About this book

The Code of Federal Regulations of the United States of America

1981 - 524 pages
...paymant under this contract. 5. TERMINATION FOR DEFAULT— DAMAGES FOR DELAY— TlMC EXTENSIONS (a) If the Contractor refuses or fails to prosecute the...will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1969 - 640 pages
...prescribed in § l-8.700-2(b) (4) : TERMINATION FOR DEFAULT — DAMAGES FOR DELAY — TIME EXTENSIONS (a) If the Contractor refuses or fails to prosecute the...will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1983 - 1104 pages
...in excess of siofooo. TERMINATION FOR DEFAULT-DAMAGES FOR DELAY-TIME EXTENSIONS (OCTOBER 1969) (a) If the Contractor refuses or fails to prosecute the...will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government...