" Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may... "
The Code of Federal Regulations of the United States of America - Page 373
1966
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 148

United States. Court of Claims, Audrey Bernhardt - 1962 - 784 pages
...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute..."Disputes." However, nothing in this clause shall excuse the Con148 c. Os. Per Cariam tractor from proceeding with the contract as changed. * * * * * 12. DISPUTES...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1955 - 1316 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change:...must be asserted may be varied in accordance with Department procedures. CODIFICATION: § 7.103-2 was revised by Amendment 14, 21 FB 6410, Aug. 25, 1956,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1969 - 752 pages
...in the contract price or delivery schedule, or both, and the contract shall be modified in writing accordingly. Any claim by the Contractor for adjustment...entitled "Disputes". However, nothing In this clause •hall excuse the Contractor from proceeding with the contract as changed. In the foregoing clause,...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1979 - 1186 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change,...Contractor from proceeding with the contract as changed. (End of cbiuel In the foregoing clause, the period of "30 days" within which any claim for adjustment...
Full view - About this book

The Code of Federal Regulations of the United States of America

1982 - 532 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change....Contractor from proceeding with the contract as changed. § 15-7.150-2 Inspection of services. Insert the following clause only in service contracts other than...
Full view - About this book

The Code of Federal Regulations of the United States of America

1975 - 1236 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change,...Contractor from proceeding with the contract as changed. (End of clause) In the foregoing clause, the period of "30 days" within which any claim for adjustment...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1982 - 712 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...the contract as changed. In the foregoing clause the pehod of "30 days" within which any claim for adjustment must be asserted may be varied not to exceed...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1981 - 676 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...Contractor from proceeding with the contract as changed. § 1-7.102-3 Extras. EXTRAS Except as otherwise provided in this contract, no payment for extras shall...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1993 - 664 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...Contractor from proceeding with the contract as changed. (End of clause) CLAUSE No. 20— RETROCESSION (JUNE 1977) (a) The Indian tribe that initially requested...
Full view - About this book

The Code of Federal Regulations of the United States of America

1971 - 664 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...Contractor from proceeding with the contract as changed. 3. EXTRAS Except as otherwise provided in this contract, no payment for extras shall be made unless...