" Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 116
1972
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 154

United States. Court of Claims, Audrey Bernhardt - 1968 - 922 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 145

United States. Court of Claims, Audrey Bernhardt - 1959 - 820 pages
...that "Any claim by the contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the contractor of the notification of change," and the requirement that any disputes concerning a question of fact resulting from the change shall...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 141

United States. Court of Claims, Audrey Bernhardt - 1959 - 1028 pages
...claim of the Contractor for adjustment under this Clause must be asserted in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer, if he decides that the facts justify...
Full view - About this book

Specifications for Gun Forgings for the United States Army and Navy, August 1918

United States. Army. Ordnance Department. War Department - 1926 - 36 pages
...caliber, two months. (4) All other gun forgings, six weeks. The above-mentioned time allowances shall date from the date of receipt by the contractor of the notification of rejection. If these times of replacement are exceeded the department may grant such extensions as the...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1988 - 1120 pages
...Contractor (i) to increase or decrease plant protection and physical security devices and equipment and (ii) to increase or decrease the number of Contractor personnel...considered a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." However, nothing in this clause...
Full view - About this book

The Code of Federal Regulations of the United States of America

1972 - 220 pages
...increase or decrease plant protection and physical security devices and equipment and (11) to lucre;'. HO or decrease the number of Contractor personnel assigned...considered a dispute concerning a question of fact within tne meaning of the clause of this contract entitled "Disputes." However, nothing in this clause...
Full view - About this book

The Code of Federal Regulations of the United States of America

1975 - 252 pages
...adjustment shall be made In the contract price or delivery schedule or both and the contract chalí be modified in writing accordingly. Any claim by the...justify such action, may receive and act upon any such «laim asserted at any tune prior to final payment •under the contract. Failure to agree to any adjustment...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1982 - 690 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1976 - 1228 pages
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the dale of receipt by the Contractor of the notification of...asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1970 - 984 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the...receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...