... FINDINGS OF FACT The court , having considered the evidence , the report of Trial Commissioner Mastin G. White , and the briefs and argument of counsel , makes findings of fact as follows : 1 1. The plaintiff , Terminal Construction ...
... FINDINGS OF FACT The court , having considered the evidence , the report of Trial Commissioner Mastin G. White , and the briefs and argument of counsel , makes findings of fact as follows : 1 1. The plaintiff , Terminal Construction ...
Page 187
United States. Court of Claims. 178 Findings of Fact regarding reenlistment and was advised that authority to reenlist had to be established at or prior to the date of sepa ... Findings of Fact 171 Ct . Cl . Housing Officer EDWARD W. COLE ...
United States. Court of Claims. 178 Findings of Fact regarding reenlistment and was advised that authority to reenlist had to be established at or prior to the date of sepa ... Findings of Fact 171 Ct . Cl . Housing Officer EDWARD W. COLE ...
Page 295
... findings so as to narrow the issues for con- sideration on appeal . At a prehearing conference on March 26 , 1958 , before a trial examiner of the Board , it was agreed that the contracting officer would make new findings of fact ...
... findings so as to narrow the issues for con- sideration on appeal . At a prehearing conference on March 26 , 1958 , before a trial examiner of the Board , it was agreed that the contracting officer would make new findings of fact ...
Other editions - View all
Common terms and phrases
Acme Acme's action adjustment administrative agreement Air Force amount appeal Army basis Board breach cancellation Capehart Housing captains change order Clinton County cofferdam Company concrete contingent fees contract price contracting officer Corp costs Court 171 Ct damages decision deductions defendant defendant's delay delivery depletion determination employee entitled to recover equipment evidence expenditures expenses Fact 171 Ct February 19 filed Findings of Fact Government grade incurred issued June June 11 Kennecott Kentucky National Guard Lansdale latex letter liquidated damages machine Manalapan manganese March ment Metals mining Norris October October 23 operation Opinion of Commissioner paid parties patent payment percent performance piles plaintiff prime contractor prior production reasonable record requested rifles schedule settlement sewer specifications subcontractor substitute facilities Supp supra surface texture termination claim tiff tion Tract Tucker United USSRMCO Utah Copper wage Watervliet Arsenal