Page 217
... adjustment in the contract price necessitated by any change in the pre- vailing wage schedule . Basically , as plaintiff points out , the making of the adjustment required ( 1 ) ascertainment of the number of man - hours for each wage ...
... adjustment in the contract price necessitated by any change in the pre- vailing wage schedule . Basically , as plaintiff points out , the making of the adjustment required ( 1 ) ascertainment of the number of man - hours for each wage ...
Page 321
... adjustment for loss of $ 14,782.63 . We think these facts establish the mutual understanding of the parties to the subcontract with respect to adjustment for loss , and an admission that an adjustment for loss in at least that amount ...
... adjustment for loss of $ 14,782.63 . We think these facts establish the mutual understanding of the parties to the subcontract with respect to adjustment for loss , and an admission that an adjustment for loss in at least that amount ...
Page 761
... Adjustment of bid price for prevailing wage increases . Determination of price adjustment by Federal Housing Com- missioner . What constitutes . Where , prior to closing under a Capehart Housing contract , the Secretary of Labor makes a ...
... Adjustment of bid price for prevailing wage increases . Determination of price adjustment by Federal Housing Com- missioner . What constitutes . Where , prior to closing under a Capehart Housing contract , the Secretary of Labor makes a ...
Other editions - View all
Common terms and phrases
Acme Acme's action adjustment administrative agreement Air Force amount appeal Army basis Board breach cancellation Capehart Housing captains change order Clinton County cofferdam Company concrete contingent fees contract price contracting officer Corp costs Court 171 Ct damages decision deductions defendant defendant's delay delivery depletion determination employee entitled to recover equipment evidence expenditures expenses Fact 171 Ct February 19 filed Findings of Fact Government grade incurred issued June June 11 Kennecott Kentucky National Guard Lansdale latex letter liquidated damages machine Manalapan manganese March ment Metals mining Norris October October 23 operation Opinion of Commissioner paid parties patent payment percent performance piles plaintiff prime contractor prior production reasonable record requested rifles schedule settlement sewer specifications subcontractor substitute facilities Supp supra surface texture termination claim tiff tion Tract Tucker United USSRMCO Utah Copper wage Watervliet Arsenal