Page 162
... allowed as reimbursement for overhead and related expenses over and above the direct costs of extra work covered by a change order . Defendant sometimes actually allowed 10 percent near the completion of the contract . 70 Findings of ...
... allowed as reimbursement for overhead and related expenses over and above the direct costs of extra work covered by a change order . Defendant sometimes actually allowed 10 percent near the completion of the contract . 70 Findings of ...
Page 174
... allowed payments and backcharges totaling $ 95,267.88 , thus resulting in an allowance for plaintiff on its ... allowed a total of $ 101,296.06 consisting of the subcontract amount of $ 72,533 , plus $ 28,763.06 for additional work ...
... allowed payments and backcharges totaling $ 95,267.88 , thus resulting in an allowance for plaintiff on its ... allowed a total of $ 101,296.06 consisting of the subcontract amount of $ 72,533 , plus $ 28,763.06 for additional work ...
Page 314
... allowed $ 2,750 for this item , computed at the rate of $ 50 per day for 55 days ( roughly 440 hours which corresponds to the 443 hours found by the contracting officer ) , and stated as follows : Appellant offered testimony in general ...
... allowed $ 2,750 for this item , computed at the rate of $ 50 per day for 55 days ( roughly 440 hours which corresponds to the 443 hours found by the contracting officer ) , and stated as follows : Appellant offered testimony in general ...
Other editions - View all
Common terms and phrases
Acme Acme's action adjustment administrative agreement Air Force amount appeal Army basis Board breach cancellation Capehart Housing captains change order Clinton County cofferdam Company concrete contingent fees contract price contracting officer Corp costs Court 171 Ct damages decision deductions defendant defendant's delay delivery depletion determination employee entitled to recover equipment evidence expenditures expenses Fact 171 Ct February 19 filed Findings of Fact Government grade incurred issued June June 11 Kennecott Kentucky National Guard Lansdale latex letter liquidated damages machine Manalapan manganese March ment Metals mining Norris October October 23 operation Opinion of Commissioner paid parties patent payment percent performance piles plaintiff prime contractor prior production reasonable record requested rifles schedule settlement sewer specifications subcontractor substitute facilities Supp supra surface texture termination claim tiff tion Tract Tucker United USSRMCO Utah Copper wage Watervliet Arsenal