Page 96
... authorization . By that time the cast - iron pipe originally proposed was unavailable . Plaintiff so ad- vised defendant ... authorized to do the necessary corrective work , ' which was almost a year after defendant was made ' Defendant ...
... authorization . By that time the cast - iron pipe originally proposed was unavailable . Plaintiff so ad- vised defendant ... authorized to do the necessary corrective work , ' which was almost a year after defendant was made ' Defendant ...
Page 111
... authorized representative . Any claim for adjustment under this article must be asserted within 10 days from the date the change is ordered : Provided , however , That the contracting officer , if he determines that the facts justify ...
... authorized representative . Any claim for adjustment under this article must be asserted within 10 days from the date the change is ordered : Provided , however , That the contracting officer , if he determines that the facts justify ...
Page 384
... authorized representative , that gratuities ( in the form of enter- tainment , gifts , or otherwise ) were offered or given by the Contractor , or any agent or representative of the Contractor , to any officer or employee of the Govern ...
... authorized representative , that gratuities ( in the form of enter- tainment , gifts , or otherwise ) were offered or given by the Contractor , or any agent or representative of the Contractor , to any officer or employee of the Govern ...
Other editions - View all
Common terms and phrases
Acme Acme's action adjustment administrative agreement Air Force amount appeal Army basis Board breach cancellation Capehart Housing captains change order Clinton County cofferdam Company concrete contingent fees contract price contracting officer Corp costs Court 171 Ct damages decision deductions defendant defendant's delay delivery depletion determination employee entitled to recover equipment evidence expenditures expenses Fact 171 Ct February 19 filed Findings of Fact Government grade incurred issued June June 11 Kennecott Kentucky National Guard Lansdale latex letter liquidated damages machine Manalapan manganese March ment Metals mining Norris October October 23 operation Opinion of Commissioner paid parties patent payment percent performance piles plaintiff prime contractor prior production reasonable record requested rifles schedule settlement sewer specifications subcontractor substitute facilities Supp supra surface texture termination claim tiff tion Tract Tucker United USSRMCO Utah Copper wage Watervliet Arsenal