Cases Decided in the Court of Claims of the United States, Volumes 160-171 |
From inside the book
Results 1-3 of 14
Page 528
... latex . Nevertheless , Toyad's bid to plaintiff , and consequently plaintiff's bid to defendant , was figured on a price of 34 cents per pound , allowing seven and a half cents as a contingency for any price rise that could reasonably ...
... latex . Nevertheless , Toyad's bid to plaintiff , and consequently plaintiff's bid to defendant , was figured on a price of 34 cents per pound , allowing seven and a half cents as a contingency for any price rise that could reasonably ...
Page 529
... latex . The charge does not include any amounts for labor used in the handling . It is solely the actual loss of material . ( 4 ) Liquid latex is perishable and requires controlled storage conditions . Under proper conditions it can be ...
... latex . The charge does not include any amounts for labor used in the handling . It is solely the actual loss of material . ( 4 ) Liquid latex is perishable and requires controlled storage conditions . Under proper conditions it can be ...
Page 530
... latex under purchase order 1945 , dated June 5 , 1950 . 57. Latex storage capacity . In July of 1950 the total tank storage capacity of Toyad was 38,753 gallons . This was increased in January 1951 to 40,753 by the addition of one 2,000 ...
... latex under purchase order 1945 , dated June 5 , 1950 . 57. Latex storage capacity . In July of 1950 the total tank storage capacity of Toyad was 38,753 gallons . This was increased in January 1951 to 40,753 by the addition of one 2,000 ...
Other editions - View all
Common terms and phrases
Acme Acme's action adjustment administrative agreement Air Force amount appeal Army basis Board breach cancellation Capehart Housing captains change order Clinton County cofferdam Company concrete contingent fees contract price contracting officer Corp costs Court 171 Ct damages decision deductions defendant defendant's delay delivery depletion determination employee entitled to recover equipment evidence expenditures expenses Fact 171 Ct February 19 filed Findings of Fact Government grade incurred issued June June 11 Kennecott Kentucky National Guard Lansdale latex letter liquidated damages machine Manalapan manganese March ment Metals mining Norris October October 23 operation Opinion of Commissioner paid parties patent payment percent performance piles plaintiff prime contractor prior production reasonable record requested rifles schedule settlement sewer specifications subcontractor substitute facilities Supp supra surface texture termination claim tiff tion Tract Tucker United USSRMCO Utah Copper wage Watervliet Arsenal