" The Contracting Officer may at any time, by a written order, and without notice to the sureties, make changes in the drawings and/or specifications of this contract and within the general scope thereof. If such changes cause an increase or decrease in... "
The Code of Federal Regulations of the United States of America - Page 282
1964
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 126

United States. Court of Claims, Audrey Bernhardt - 1954 - 1160 pages
...written order, and without notice to the sureties, make changes in the drawings and (or) specificacations of this contract and within the general scope thereof....shall be made and the contract shall be modified in writing accordingly. No change involving an estimated increase or decrease of more than $500 shall...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 98

United States. Court of Claims - 1943 - 906 pages
...time, by a written order, and without notice to the sureties, make changes in the drawings and (or) specifications of this Contract and within the general...equitable adjustment shall be made and the contract snail be modified in writing accordingly. No change involving an estimated increase or decrease of...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 119

United States. Court of Claims, Audrey Bernhardt - 1951 - 968 pages
...drawings and/or specifications of this contract and within the general scope 707 ~ - ' - Findings of F!«t thereof. If such changes cause an increase or decrease...shall be made and the contract shall be modified in writing accordingly. * * * ARTICLE 4. Changed conditions. — Should the contractor encounter, or the...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 95

United States. Court of Claims - 1942 - 868 pages
...thereof and the contract provided for changes being made but Article 3 (see finding 6) provided that "If such changes cause an increase or decrease in...shall be made and the contract shall be modified in writing accord314 Opinion of the Court ingly." The contracting officer paid no attention to the provision...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 132

United States. Court of Claims, Audrey Bernhardt - 1955 - 936 pages
...drawings and/or specifications of this contract within the general scope thereof. If such changes cause increase or decrease in the amount due under this...shall be modified in writing accordingly. Any claim for adjustment under this article must be asserted within 10 days from the date the change is ordered...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 133

United States. Court of Claims, Audrey Bernhardt - 1956 - 1104 pages
...without notice to the sureties, make changes in the drawings and/or specifications or this contract within the general scope thereof. If such changes...performance, an equitable adjustment shall be made ana the contract shall be modified in writing accordingly. Any claim for adjustment under this article...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 137

United States. Court of Claims, Audrey Bernhardt - 1957 - 1028 pages
...specifications of this contract within the general scope thereof. If such changes cnuse an iiicrease or decrease in the amount due under this contract,...shall be modified in writing accordingly. Any claim for Findings of Fact adjustment under this article must be asserted within 10 days from the date the...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 114

United States. Court of Claims, Audrey Bernhardt - 1950 - 824 pages
...general scope thereof. If such changes cause an increase or decrease 571 Reporter's Statement of the Case in the amount due under this contract, or in the time...shall be modified in writing accordingly. Any claim for adjustment under this article must be asserted within 10 days from the date the change is ordered:...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 96

United States. Court of Claims - 1943 - 672 pages
...order, and without notice to the sureties, make changes in the drawings and (or) specifications ot this contract and within the general scope thereof....contract, or in the time required for its performance, nn equitable adjustment shall be made and the contract shall be modified in writing accordingly. ....
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 91

United States. Court of Claims - 1940 - 772 pages
...time, by a written order, and without notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general...amount due under this contract, or in the time required Reporter's Statement of the Case for its performance, an equitable adjustment shall be made and the...