| United States. Congress. House. Committee on Armed Services - 1960 - 1930 pages
...Contractor niaib or otherwise furnishes to the Contracting Officer a written npi>eiil addressed tc the Secretary. The decision of the Secretary or his...bad faith, or not supported by substantial evidence. In connection with any appeal prrx-eeding under this clause, the Contractor shall be afforded an opportunity... | |
| 1973 - 740 pages
...in § 1— 8.700-2 (b)(l). § 1-7.102-12 Disputes. DISPUTES (a) Except as otherwise provided In this contract, any dispute concerning a question of fact...bad faith, or not supported by substantial evidence. In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity... | |
| 1976 - 864 pages
...purchase orders under this contract. Clause No. 2 — Disputes. (a) Except as otherwise provided In this contract, any dispute concerning a question of fact...bad faith, or not supported by substantial evidence. In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity... | |
| 1964 - 432 pages
...agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor....bad faith, or not supported by substantial evidence. In connection with any appeal proceeding' under this clause, the Contractor shall be afforded an opportunity... | |
| 1979 - 1304 pages
...agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor....bad faith, or not supported by substantial evidence. In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity... | |
| 1980 - 582 pages
...The decision of the contracting officer shall be final and conclusive unless within thirty (30) days from the date of receipt of such copy, the contractor...bad faith, or not supported by substantial evidence. In connection with any appeal proceeding under this clause, the contractor shall be afforded an opportunity... | |
| 1979 - 520 pages
...The decision of the contracting officer shall be final and conclusive unless within thirty (30) days from the date of receipt of such copy, the contractor...bad faith, or not supported by substantial evidence. In connection with any appeal proceeding under this clause, the contractor shall be afforded an opportunity... | |
| 1972 - 684 pages
...Contracting Officer shall be final ana. unless, within 30 days from the date of reciept of such U'jiy, the Contractor mails or otherwise furnishes to the...bad faith, or not supported by substantial evidence. In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity... | |
| 1969 - 752 pages
...final and conclusive unless, within 30 days from the date of receipt of such copy, the Contractor malls or otherwise furnishes to the Contracting Officer...bad faith, or not supported by substantial evidence. In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity... | |
| 1970 - 670 pages
...final and conclusive unless within 30 days from the date of receipt of such copy, the Contractor malls or otherwise furnishes to the Contracting Officer...bad faith, or not supported by substantial evidence. In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity... | |
| |