| United States. Court of Claims, Audrey Bernhardt - 1963 - 938 pages
...defaults of subcontractors due to any of such causes unless the Contracting Officer shall determine that the supplies or services to be furnished by the subcontractor...sources in sufficient time to permit the Contractor to meet the required delivery schedule. (0) In the event the Government terminates this contract in whole... | |
| United States. Court of Claims, Audrey Bernhardt - 1959 - 1028 pages
...performance because the contracting officer made no determination that the supplies defaulted by Hatheway were obtainable from other sources in sufficient time to permit the contractor to meet the required delivery schedule. The provision is to the contrary, and without ambiguity says that,... | |
| United States. Congress. House. Committee on Armed Services - 1960 - 1930 pages
...defaults of subcontractors due to any of such causes unless the contracting officer shall determine that the supplies or services to be furnished by the sub-contractor...obtainable from other sources in sufficient time to |M>rmit the contractor to meet the required schedule. 4. Disputes. — (a) Except as otherwise provided... | |
| 2002 - 726 pages
...control and without the fault or negligence of the Contractor. Examples of such causes include nets of God or of the public enemy, acts of the Government...to perform the job order within the time specified. id) If the Government terminates the job order in whole or in part as provided in paragraph (a) of... | |
| 1973 - 968 pages
...of both the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor shall not be liable for any excess costs...sources In sufficient time to permit the Contractor to meet the required delivery schedule or other performance requirements. (d) If this contract Is terminated... | |
| 1968 - 1348 pages
...of both the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor shall not be liable for any excess costs...sources In sufficient time to permit the Contractor to meet the required delivery schedule. (d) If this contract Is terminated as provided In paragraph (a)... | |
| 1967 - 686 pages
...the fault or negligence of either of them, the Contractor shall Title 41— Chapter 6 § 6-7.101-22 not be liable for any excess costs for failure to...sources in sufficient time to permit the Contractor to meet the required delivery schedule. (d) If this contract is terminated as provided in paragraph (a)... | |
| 1985 - 564 pages
...perform is caused by the default of a subcontractor at any tier, and if the cause of the default is beyond the control of both the Contractor and subcontractor,...any excess costs for failure to perform, unless the subcontracted supplies or services were obtainable from other sources in sufficient time for the Contractor... | |
| 1994 - 690 pages
...perform is caused by the default of a subcontractor at any tier, and If the cause of the default is beyond the control of both the Contractor and subcontractor,...any excess costs for failure to perform, unless the subcontracted supplies or services were obtainable from other sources in sufficient time for the Contractor... | |
| 2000 - 928 pages
...caused by the default of a subcontractor, the purchaser shall not be determined to be in default or to be liable for any excess costs for failure to perform,...from other sources in sufficient time to permit the purchaser to meet the delivery schedule, if: (i) Such default arises out of causes beyond the control... | |
| |