" CHANGES The Contracting Officer may at any time, by a written order, and without notice to the sureties, make changes, within the general scope of this contract, in any one or more of the following... "
The Code of Federal Regulations of the United States of America - Page 17
1949
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volumes 120-130

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 pages
...are believed to be approximately correct. ***** The contract provided in part as follows : ARTICLE 3. Changes. — The contracting officer may at any...such changes cause an increase or decrease in the amout due under this contract ,or in the time required for its performance, an equitable adjustment...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 114

United States. Court of Claims, Audrey Bernhardt - 1950 - 824 pages
...specifically provided for in the contract. The contract contained the following provisions : ARTICLE 3. Changes. — The contracting officer may at any...thereof. If such changes cause an increase or decrease 571 Reporter's Statement of the Case in the amount due under this contract, or in the time required...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 119

United States. Court of Claims, Audrey Bernhardt - 1951 - 968 pages
...copy was sent to it on February 26, 1943. 5. Pertinent provisions of the contract provided : ARTICLE 3. Changes, — The contracting officer may at any...specifications of this contract and within the general scope 707 ~ - ' - Findings of F!«t thereof. If such changes cause an increase or decrease in the amount...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 132

United States. Court of Claims, Audrey Bernhardt - 1955 - 936 pages
...61,200 Cu. yd 3 62 Findings of Fact as he may consider necessary, unless otherwise provided. ARTICLE 3. Changes. — The contracting officer may at any...the drawings and/or specifications of this contract within the general scope thereof. If such changes cause increase or decrease in the amount due under...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 109

United States. Court of Claims - 1948 - 974 pages
...the total estimated consideration was $954,452.24. Article 3 of the contract provided as follows : Changes. — The contracting officer may at any time,...the drawings and/or specifications of this contract within the general scope thereof. If such changes cause an increase or decrease in the amount due under...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 137

United States. Court of Claims, Audrey Bernhardt - 1957 - 1028 pages
...proper deduction in accordance with "Article 3. Changes" of the contract. Article 3 provides : The contracting officer may at any time, by a written...the drawings and/or specifications of this contract within the general scope thereof. If such changes cnuse an iiicrease or decrease in the amount due...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 118

United States. Court of Claims, Audrey Bernhardt - 1951 - 840 pages
...-which amount was paid to plaintiff. 3. The contract provided, among other things, as follows: ARTICLE 3. Changes. — The Contracting Officer may at any...the sureties, make changes in the drawings and/or specification of this Contract and within the general scope thereof. If such changes cause an increase...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 116

United States. Court of Claims, Audrey Bernhardt - 1950 - 1004 pages
...and Consolidated Builders, Inc., as CBI 14. Certain articles of the contract read as follows : ART. 3. Changes. — The contracting officer may at any...notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general scope thereof. If such changes cause...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - 1948 - 886 pages
...188 days at $25 per day, or a total of $4,700. 9. The contract provided, in part, as follows : ART. 3. Changes. — The contracting officer may at any...notice to the sureties, make changes in the drawings and (or) specifications of this contract and within the general scope thereof. If such changes cause...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 101

United States. Court of Claims - 1944 - 960 pages
...time, by a written order, and without notice to the sureties, make changes in the drawings and (or) specifications of this Contract and within the general...cause an increase or decrease in the amount due under the Contract, or in the time required for its performance, an equitable adjustment shall be made and...