...performance of this contract. When and to the extent that the estimated cost set forth in the Schedule has been increased, any costs incurred by the Contractor...had been incurred after such increase in estimated coat 7.451-3 Allowable Coat and Payment. Insert the clause set forth below. ALLOWABLE COST AND PAYMENT... | |
| 1998 - 656 pages
...estimated cost set forth in this contract has been increased by the Contracting Officer in writing, any costs incurred by the Contractor in excess of...been incurred after such increase in estimated cost. (End of clause) CLAUSE No. 4 — ALLOWABLE COST (JUN 1977) (a) Compensation for Contractor's performance.... | |
| 1989 - 660 pages
...estimated cost set forth In this contract has been increased by the Contracting Officer in writing, any costs incurred by the Contractor in excess of...been incurred after such Increase in estimated cost. (End of clause) CLAUSE No. 4 — ALLOWABLE COST ( JTXNE 1977) (a) Compensation for Contractor's performance.... | |
| 1974 - 720 pages
...cost set forth In this contract has been Increased by the Contracting Officer In writing, any cost Incurred by the Contractor in excess of such estimated...been Incurred after such Increase in estimated cost, (c) If, (1) the Contractor stops performance before completion of all work hereunder because It has... | |
| 1972 - 1094 pages
...performance of this contract. When and to the extent that the estimated cost set forth in the Schedule has been increased, any costs incurred by the Contractor...cost shall be allowable to the same extent as if such cost had been incurred after such Increase in estimated cost. § 18-7.402-3 Allowable cost, fixed fee,... | |
| 1984 - 720 pages
...has been increased, any costs incurred by the Contractor in excess of the amount previously allotted shall be allowable to the same extent as if such costs had been incurred after such increase in the amount allotted; unless the Contracting Officer issues a termination or other notice and directs... | |
| 1981 - 706 pages
...foregoing manner, costs incurred prior to such increase, though in excess of the previous estimated costs shall be allowable to the same extent as if such costs had been incurred after such increase. (c) Written directions issued pursuant to the clause of this contract entitled "Changes" shall not... | |
| 1966 - 968 pages
...governing such Increases. When and to the extent that the estimated total cost set forth In the Schedule has been Increased, any costs incurred by the Contractor in excess of such estimated total cost prior to the Increase in such estimated total cost shall be allowable to the same extent... | |
| 1974 - 1020 pages
...cost of performing such work. When and to the extent that the estimated cost set forth In the Schedule has been Increased, any costs incurred by the Contractor In excess of such § 18-7.702-12 estimated cost prior to the Increase In estimated cost shall be allowable to the same... | |
| 1982 - 520 pages
...estimated cost has been increased, any costs previously incurred by the contractor in excess of such estimated cost shall be allowable to the same extent as if such costs are incident to and necessary for the performance of work specifically authorized under this contract... | |
| |