" ... unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract... "
Relating to Labor Practices of Employers of Labor in the Shipbuilding ... - Page 77
by United States. Congress. House. Committee on Labor - 1935 - 161 pages
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 109

United States. Court of Claims - 1948 - 974 pages
...the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted...strikes, freight embargoes, and unusually severe weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 98

United States. Court of Claims - 1943 - 906 pages
...in the completion of the work due to unforseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted...restrictions, strikes, freight embargoes, and unusually Reporter's Statement of the Case severe weather or delays of subcontractors due to such causes: Provided...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 126

United States. Court of Claims, Audrey Bernhardt - 1954 - 1160 pages
...unforeseeable causes beyond the control and without the fault or negligence of the 126 C.CU. Finding* of Fact contractor, including, but not restricted to, acts...strikes, freight embargoes, and unusually severe weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 122

United States. Court of Claims, Audrey Bernhardt - 1952 - 936 pages
...contractor in making deliveries is due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted...quarantine restrictions, strikes, freight embargoes, unusually severe weather, and delays of a subcontractor due to such causes unless the contracting officer...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 128

United States. Court of Claims, Audrey Bernhardt - 1954 - 918 pages
...unforeseeable causes beyond the control and without the fault or negligence of 299 Finding* of F.ct the contractor, including, but not restricted to,...quarantine restrictions, strikes, freight embargoes, unusually severe weather, and delays of a subcontractor due to such causes unless the contracting officer...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 152

United States. Court of Claims, Audrey Bernhardt - 1963 - 938 pages
...beyond the control and without the fault or negligence of the Contractor. Such causes include, but are not restricted to, acts of God or of the public enemy,...quarantine restrictions, strikes, freight embargoes, unusually severe weather, and defaults of subcontractors due to any of Findings of Fact such causes...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - 1948 - 886 pages
...the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted...God, or of the public enemy, acts of the Government or any state or political subdivision thereof (including, but not restricted to the operation of any...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volumes 120-130

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 pages
...completion of the work due to unforeseeable causes beyond the control and without the fault or negligence or the contractor, including, but not restricted to,...God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 131

United States. Court of Claims, Audrey Bernhardt - 1955 - 908 pages
...without the fault or negligence of the Contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods,...quarantine restrictions, strikes, freight embargoes, unusually severe weather, and delays of a subcontractor due to such causes unless the Contracting Officer...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 101

United States. Court of Claims - 1944 - 960 pages
...public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine...strikes, freight embargoes, and unusually severe weather or delays of subcontractors due to such causes, if the contractor shall within 10 days from the beginning...