| United States. Court of Claims, Audrey Bernhardt - 1952 - 936 pages
...or supplies In the open market or secure the manufacture and delivery of the materials and supplies by contract or otherwise, and the contractor and his...Government thereby : Provided, That the contractor •ball not be charged with any excess cost occasioned the Government by the purchase of materials... | |
| United States. Court of Claims, Audrey Bernhardt - 1962 - 784 pages
...market or secure the manufacture and delivery of the materials and supplies by 49 Finding* of Fact contract or otherwise, and the contractor and his...any excess cost occasioned the Government thereby : * * * 41. Prior to termination of the contract, a representative of CAA, in order to ascertain whether... | |
| United States. Court of Claims, Audrey Bernhardt - 1955 - 936 pages
...extension thereof * * *, the Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor and his...liable to the Government for any excess cost occasioned * * * thereby." 2 21. The specifications provided : 3 The grading of the site, being performed by others,... | |
| United States. Court of Claims - 1944 - 960 pages
...contract, and purchase in the open market the undelivered portion or the supplies covered by the contract, and the contractor and his sureties shall be liable...any excess cost occasioned the Government thereby. 3. On October 3, 1933, goods of a total value of $4,384.85 had been delivered. The balance of $310.80... | |
| United States. Court of Claims - 1946 - 936 pages
...event the original contractor defaulted and the Government completed the work by contract or otherwise, "the contractor and his sureties shall be liable to...any excess cost occasioned the Government thereby." Art. 15 made the decisions of the contracting officer and the head of the Department final on all disputes... | |
| United States. Court of Claims, Audrey Bernhardt - 1950 - 1004 pages
...as to which there has been a failure to pay said required wages and prosecute the work to completion by contract or otherwise, and the contractor and his...sureties shall be liable to the Government for any excess costs occasioned the Government thereby. ARTICLE 24. Payment and Performance Bonds. — The contractor... | |
| United States. Court of Claims, Audrey Bernhardt - 1952 - 1040 pages
...take over the work and prosecute the same to completion, hy contract or otherwise, and the contractqr and his sureties shall be liable to the Government...any excess cost occasioned the Government thereby. If the contractor's right to proceed is so terminated, the Government may take possession of and utilize... | |
| United States. Court of Claims - 1948 - 886 pages
...or supplies in the open market or secure the manufacture and delivery of the materials and supplies by contract or otherwise, and the contractor and his sureties shall be liable to the Government thereby; Provided, that the contractor shall not be charged with any excess cost occasioned the Government... | |
| United States. Court of Claims, Audrey Bernhardt - 1958 - 966 pages
...the work and prosecute the same to completion, by contract or otherwise, and the contractor and nis sureties shall be liable to the Government for any excess cost occasioned the Government thereby. If the contractor's right to proceed is so terminated, the Government may take possession of and utilize... | |
| United States. Court of Claims, Audrey Bernhardt - 1951 - 968 pages
...which it may have, may procure similar articles or obtain similar services elsewhere and the Contractor shall be liable to the Government for any excess cost occasioned the Government thereby: Provided, however, That the contract may not be terminated under this Article and the Contractor shall not be... | |
| |