" ... unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government... "
Decisions of the Comptroller General of the United States - Page 534
by United States. General Accounting Office - 1928
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 100

United States. Court of Claims - 1944 - 656 pages
...any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including,...That the contractor shall within ten days from the be100 C. Cls. Reporter's Statement of the Case ginning of any such delay notify the contracting officer...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 93

United States. Court of Claims - 1941 - 858 pages
...any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including,...Provided further, That the contractor shall within 10 days from the beginning of any such delay notify the contracting officer in writing of the causes...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 84

United States. Court of Claims - 1937 - 710 pages
...of the contractor in making deliveries is due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including,...strikes, freight embargoes, and unusually severe weather, but not including delays caused by subcontractors : Provided further. That the contractor shall within...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 98

United States. Court of Claims - 1943 - 906 pages
...any delays in the completion of the work due to unforseeable causes beyond the control and without the fault or negligence of the contractor, including,...restrictions, strikes, freight embargoes, and unusually Reporter's Statement of the Case severe weather or delays of subcontractors due to such causes: Provided...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 122

United States. Court of Claims, Audrey Bernhardt - 1952 - 936 pages
...of the contractor in making deliveries is due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including,...quarantine restrictions, strikes, freight embargoes, unusually severe weather, and delays of a subcontractor due to such causes unless the contracting officer...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 128

United States. Court of Claims, Audrey Bernhardt - 1954 - 918 pages
...unforeseeable causes beyond the control and without the fault or negligence of 299 Finding* of F.ct the contractor, including, but not restricted to,...quarantine restrictions, strikes, freight embargoes, unusually severe weather, and delays of a subcontractor due to such causes unless the contracting officer...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 152

United States. Court of Claims, Audrey Bernhardt - 1963 - 938 pages
...beyond the control and without the fault or negligence of the Contractor. Such causes include, but are not restricted to, acts of God or of the public enemy,...quarantine restrictions, strikes, freight embargoes, unusually severe weather, and defaults of subcontractors due to any of Findings of Fact such causes...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volumes 120-130

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 pages
...completion of the work due to unforeseeable causes beyond the control and without the fault or negligence or the contractor, including, but not restricted to,...God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 103

United States. Court of Claims - 1946 - 906 pages
...Employment Service, fires, floods, epidemics, quarantine restrictions, strikes, freight emoargoes, and unusually severe weather or delays of subcontractors...Provided further, That the contractor shall within 10 days from the beginning of any such delay notify the contracting officer in writing of the causes...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 131

United States. Court of Claims, Audrey Bernhardt - 1955 - 908 pages
...any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or of the pub245 Findings of Fact lie enemy, acts of the Government, acts of another contractor in the performance...