" If the Contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such... "
Cases Decided in the United States Court of Claims ... with Report of ... - Page 194
by United States. Court of Claims, Audrey Bernhardt - 1952
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 7

United States. General Accounting Office - 1928 - 1012 pages
...of the standard Government construction contract is as follows : ABTICLE 9. Delays — Damages. — If the contractor refuses or fails to prosecute the...extension thereof, or fails to complete said work within such time, the Government may, by written notice to the contractor, terminate his right to proceed...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 8

United States. General Accounting Office - 1929 - 804 pages
...liquidated damages accrued to the United States. The contract provided : ABTIOLE 9. Delays — Damages. — If the contractor refuses or fails to prosecute the...or any separable part thereof, with such diligence ns will insure its completion within the time specified in article 1, or any extension thereof, or...
Full view - About this book

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - 1930 - 132 pages
...work at all times during progress, with authority to act for him. ARTICLE 9. Delays — Damages. — If the contractor refuses or fails to prosecute the...extension thereof, or fails to complete said work within such time, the Government may, by written notice to the contractor, terminate his right to proceed...
Full view - About this book

The Construction of Hoover Dam: Preliminary Investigations, Design of Dam ...

United States. Department of the Interior, Ray Lyman Wilbur, Elwood Mead - 1933 - 338 pages
...the work at all times during progress, with authority to act for him. ART. 9. Delays — Damages. — If the contractor refuses or fails to prosecute the...extension thereof, or fails to complete said work within such time, the Government may, by written notice to the contractor, terminate his right to proceed...
Full view - About this book

Orders and Regulations, Corps of Engineers, U.S. Army, 1934

United States. Army. Corps of Engineers - 1934 - 396 pages
...progress, with authority to act for him. ARTICLE 9. Delays-Damages . (a) Termination for Default. — If the contractor refuses or fails to prosecute the work, or any separable part 191 7113.89 CHANGE 13, 1 Mar 50 To Part I, Chapter VII thereof, with such diligence as will insure...
Full view - About this book

Taking the Profits Out of War: Hearings Before the Committee on Military ...

United States. Congress. House. Committee on Military Affairs - 1935 - 812 pages
...work :it all times durin:; progress, with authority to act for him. ARTICLE 1. Dclau* — Dnmape*. — If the contractor refuses or fails to prosecute the...extension thereof, or fails to complete said work within such time, the Government may, by written notice to the contractor, terminate his right to proceed...
Full view - About this book

Munitions Industry: September 4-6, 1934. Electric Boat Co

United States. Congress. Senate. Special Committee to Investigate the Munitions Industry - 1935 - 1722 pages
...or fails to prosecute the w any separable part thereof, with such diligence as will insure its com within the time specified in article 1, or any extension thereof, or fails t píete said work within such time, the Government may, by written no the contractor, terminate his...
Full view - About this book

The Code of Federal Regulations of the United States of America ..., Book 2

1939 - 1306 pages
...on the work at all times during progress, with authority to act for him. ART. 9. Delays — damages. If the contractor refuses or fails to prosecute the...specified in article 1, or any extension thereof, or falls to complete said work within such time, the Government may. by written notice to the contractor,...
Full view - About this book

United States Reports: Cases Adjudged in the Supreme Court, Volume 322

United States. Supreme Court - 1945 - 864 pages
...See H. Rep. No. 1794, p. 8 (57th Cong., 1st Bess.) ; 35 Cong. Rec. 4935. 8 "Delays — Damages. — If the contractor refuses or fails to prosecute the...extension thereof, or fails to complete said work within such time, the Government may, by written notice to the contractor, terminate his right to proceed...
Full view - About this book

United States Reports: Cases Adjudged in the Supreme Court at ..., Volume 322

United States. Supreme Court - 1945 - 862 pages
...See H. Rep. No. 1794, p. 8 (57th Cong., 1st Scss.) ; 35 Cong. Rec. 4935. 8 "Delays — Damages. — If the contractor refuses or fails to prosecute the...extension thereof, or fails to complete said work within such time, the Government may, by written notice to the contractor, terminate his right to proceed...