" Disputes. Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head... "
Cases Decided in the United States Court of Claims ... with Report of ... - Page 821
by United States. Court of Claims, Audrey Bernhardt - 1952
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - 1948 - 886 pages
...provided in this contract all disputes concerning questions of fact arising under this contract shall be decided by the Contracting Officer, subject to...written appeal by the Contractor within 30 days to the Secretary of the Navy or his duly authorized representative, whose decision shall be final and conclusive...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 29

United States. General Accounting Office - 1950 - 710 pages
...final and conclusive on the parties hereto, subject only to appeal, within 30 days, by the contractor to the head of the department concerned or his duly authorized representative: whose decision on such appeal us to the facts of delay and the extension of time for completing the work shall be...
Full view - About this book

United States Code Annotated, Volume 31

United States - 1927 - 682 pages
...cost shall be decided by Chief of Bureau subject to written appeal "by contractor to Secretary of Navy or his duly authorized representative whose decision shall be final and conclusive on parties, conscious wrongdoing or intention to cheat or be dishonest must be alleged and proved in...
Full view - About this book

Treasury Department Appropriation Bill for 1929: Hearing Before the ...

United States. Congress. House. Committee on Appropriations - 1928 - 970 pages
...promptly rendered and shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as directed. Page 9, line 3, words "legal expenses" deleted before execution. In witness whereof, the parties hereto...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 8

United States. General Accounting Office - 1929 - 804 pages
...whose decision shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as directed. ABTICLE 16. Payments to contractors. — (a) Unless otherwise provided in the specifications, partial...
Full view - About this book

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - 1930 - 132 pages
...whose decision shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as directed. ARTICLE 16. Payments to contractors. — (a) Unless otherwise provided in the specifications, partial...
Full view - About this book

Establish Uniform Requirements for Government Contracts. Hearing ... on H.R. 255

United States. U.S. Congress. House. Committee on judiciary - 1932 - 234 pages
...the head of the department concerned or his representative, and the contractor or his representative. In the meantime the contractor shall diligently proceed with the work as directed, if required by an order in writing from the head of the department concerned. In the event this board...
Full view - About this book

The Construction of Hoover Dam: Preliminary Investigations, Design of Dam ...

United States. Department of the Interior, Ray Lyman Wilbur, Elwood Mead - 1933 - 338 pages
...whose decision shall be final and conclusive upon the parties thereto as to such questions of fact. In the meantime the contractor shall diligently proceed with the work as directed. ART. 16. Payments to contractors. — (a) Unless otherwise provided in the specifications, partial...
Full view - About this book

Orders and Regulations, Corps of Engineers, U.S. Army, 1934

United States. Army. Corps of Engineers - 1934 - 396 pages
...concerning questions of fact arising under this contract shall be decided by the Deputy Contracting 0fficer subject to written appeal by the Contractor within 30 days to the Chief of Engineers or his duly authorized representative whose decision shall be final and conclusive...
Full view - About this book

Boulder Canyon Project: Final Reports

1950 - 1346 pages
...provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the Contracting Officer, subject to written appeal by the City within 30 days to the Secretary of the Navy or his duly authorized representative, whose decision...