" Officer grants a further period of time before the date of final payment under the contract), notifies the ContractIng Officer In writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend... "
Decisions of the Department of the Interior - Page 349
by United States. Department of the Interior - 1960
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 138

United States. Court of Claims, Audrey Bernhardt - 1958 - 966 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...extension? and his findings of fact thereon shall oe final and conclusive on the parties hereto, subject only to appeal, within 30 days, by the contractor...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 101

United States. Court of Claims - 1944 - 960 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...such an extension, and his findings of fact thereon 54 Reporter's Statement of the Case shall be final and conclusive on the parties hereto, subject only...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 94

United States. Court of Claims - 1942 - 818 pages
...the beginning of any such delay notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...fact justify such an extension, and his findings of facts thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 105

United States. Court of Claims - 1946 - 920 pages
...liquidated damages because of unforeseeable causes of delay, including strikes, and it provides that the contracting officer "shall ascertain the facts...judgment the findings of fact justify such an extension." This, of course, makes it mandatory upon the contracting officer to make findings of fact upon an application...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - 1948 - 886 pages
...allowed by the Contracting Officer, notify the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts...judgment the findings of fact justify such an extension. The decision of the Contracting Officer thereon shall be final, subject only to appeal under Article...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 107

United States. Court of Claims - 1947 - 806 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...of fact justify such an extension, and his findings pi fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 114

United States. Court of Claims, Audrey Bernhardt - 1950 - 824 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...his judgment the findings of fact justify such an extensionj and his findings of fact thereon shall be final and conclusive on the parties hereto, subject...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volumes 110-120

United States. Court of Claims, Audrey Bernhardt - 1952 - 932 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...completing the work when in his judgment the findings of tact justify such an extension, and his findings of fact thereon shall be final and conclusive on the...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 119

United States. Court of Claims, Audrey Bernhardt - 1951 - 968 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...time for completing the work when in his judgment the finding Findings of Fact of facts justify such an extension, and his findings of fact thereon shall...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 126

United States. Court of Claims, Audrey Bernhardt - 1954 - 1160 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...and extend the time for completing the work when in nis judgment the findings of fact justify such an extension, and his findings of fact thereon shall...