| United States. Court of Claims, Audrey Bernhardt - 1968 - 922 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| United States. Court of Claims, Audrey Bernhardt - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| 1965 - 670 pages
...completion dates, or both; and (11) such other provisions of the contract as may be so affected; and the contract shall be modified in writing accordingly....any time prior to final payment under this contract. Failure to agree at any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| 1966 - 968 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...Where the cost of property made obsolete or excess as result of a change Is included in the Contractor's claim for adjustment, the Contracting Officer shall... | |
| 1970 - 984 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...Where the cost of property made obsolete or excess as result of a change Is Included In the Contractor's claim for adjustment, the Contracting Officer shall... | |
| 1973 - 944 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...Where the cost of property made obsolete or excess as result of a change Is Included In the Contractor's claim for adjustment, the Contracting Officer shall... | |
| 1981 - 524 pages
...accordingly- Any claim by tht Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...payment under this contract. Where the cost of property mad* obsolete or excess as a result of a change is included in the Contractor's claim for adjustment,... | |
| 1976 - 436 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| 1979 - 1186 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30l days from the date of receipt by the Contractor of the...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| 1981 - 676 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| |