" That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays in the completion of the work due to unforseeable causes beyond the control and without the fault or negligence... "
To Establish Uniform Requirements for Government Contracts: Hearing Before ... - Page 61
by United States. Congress. House. Committee on the Judiciary - 1930 - 159 pages
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 87

United States. Court of Claims - 1939 - 836 pages
...defendant. SECOND CAtJSE OF ACTION Article 9 of the contract is in part as follows : Provided, That the right of the contractor to proceed shall not be...unforeseeable causes beyond the control and without the fault or negligence 0r the contractor, including, but not restricted to, acts of God * * *. The contract...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - 1948 - 886 pages
...liquidated damages for delay in completing the work and contained the following proviso : Provided, That the right of the contractor to proceed shall not be...unforeseeable causes beyond the control and without the fault or negligence of the con552 Reporter's Statement of the Case tractor, including, but not restricted...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 104

United States. Court of Claims - 1946 - 936 pages
...contract referred to in the section of the specifications just quoted was as follows: * * * Provided, That the right of the contractor to proceed shall not be...completion of the work due to unforeseeable causes 104 C. CU. Reporter's Statement of the Caie beyond the control and without the fault or negligence...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 98

United States. Court of Claims - 1943 - 906 pages
...papers and the contractor and his sureties shall be liable for the amount thereof : Provided, That the right of the contractor to proceed shall not be...of any delays in the completion of the work due to unforseeable causes beyond the control and without the fault or negligence of the contractor, including,...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 80

United States. Court of Claims - 1936 - 940 pages
...accompanying papers and the contractor and his sureties shall be liable for the amount thereof: Provided, That the right of the contractor to proceed shall not be...because of any delays in the completion of the work Reporter's Statement of the Case due to unforeseeable causes beyond the control and without the fault...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 94

United States. Court of Claims - 1942 - 818 pages
...— (Excerpt from) "Provided, That the right of the contractor to proceed shall not be determinated or the contractor charged with liquidated damages...unforeseeable causes beyond the control and without the fault or negligence of the contractor." The above quotation would be a very fair one to apply to our...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 122

United States. Court of Claims, Audrey Bernhardt - 1952 - 936 pages
...accompanying papers and the Contractor and his sureties shall be liable for the amount thereof; Provided, That the right of the Contractor to proceed shall not be...Contractor charged with liquidated damages because of any delay in the completion of the work due to unforeseeable causes beyond the control and without the...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 116

United States. Court of Claims, Audrey Bernhardt - 1950 - 1004 pages
...* Provided, That the right of the contractor to proceed shall not be terminated under this Article or the contractor charged with liquidated damages...completion of the work due to unforeseeable causes be891357—50 25 Reporter's Statement of the Case yond the control and without the fault or negligence...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 115

United States. Court of Claims, Audrey Bernhardt - 1950 - 940 pages
...part: Provided, That the right of the contractor to proceed shall not be terminated under this Article or the contractor charged with liquidated damages...of any delays in the completion of the work due to unf orseeable causes beyond the control and without the fault or negligence of the contractor, including,...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volumes 120-130

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 pages
...liable to the Government for any damages resulting from the delay as herein above stated, Provided, that the right of the contractor to proceed shall not be...terminated or the contractor charged with liquidated or actual damages because of any delays in the completion of the work due to causes beyond the control...
Full view - About this book