| United States. Court of Claims, Audrey Bernhardt - 1962 - 784 pages
...notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim..."Disputes." However, nothing in this clause shall excuse the Con148 c. Os. Per Cariam tractor from proceeding with the contract as changed. * * * * * 12. DISPUTES... | |
| United States. Court of Claims, Audrey Bernhardt - 1968 - 922 pages
...notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| 1972 - 316 pages
...notification of change; Provided, however, That the Contracting Officer, if he decides that the facts Justify such action, may receive and act upon any such claim...the Contractor from proceeding with the contract as modified. (b) In the foregoing clause the period of "sixty (60) days" within which any claim for adjustment... | |
| 1971 - 214 pages
...notification of change; Provided:, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim...the Contractor from proceeding with the contract as modified. (b) In the foregoing clause the period of "sixty (60) days" within which any claim for adjustment... | |
| 1983 - 716 pages
...notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim...nothing in this clause shall excuse the Contractor from'proceeding with the contract as changed. ยง 1-7.703-3 Extras. Insert the clause set forth in 1... | |
| 1971 - 824 pages
...Contracting Officer, If he decides that the facts Justify such action, may receive and act upon an; such claim asserted at any time prior to final payment...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "thirty (30) days" within which any claim for adjustment must... | |
| 1970 - 196 pages
...Contracting Officer, If he decides that the facts Justify such action, may receive and act upon any claim asserted at any time prior to final payment...the Contractor from proceeding with the contract as modified. (b) (1) The period of "sixty (60) days" within which any claim for adjustment must be asserted... | |
| 1981 - 706 pages
...Contracting Officer, if he decides that the facts justify such action, may receive and act upon any claim asserted at any time prior to final payment...the Contractor from proceeding with the contract as modified. (b)(1) The period of "sixty (60) days" within which any claim for adjustment must be asserted... | |
| 1982 - 1316 pages
...notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim...contract entitled "Disputes". However, nothing in thai clause shall excuse the Contractor from proceeding with the contract as changed. (End of chut)... | |
| 1975 - 172 pages
...decides that the facts justify such action, may receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure...Contractor from proceeding with the contract as changed. ;b) If this contract is executed by an AID Washington Contracting Officer, valid change orders may... | |
| |