| United States. Court of Claims, Audrey Bernhardt - 1959 - 1028 pages
...decision of the Secretary or his duly authorized representative for the hearing of such appeals shall be final and conclusive: Provided, That if no such...Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with the... | |
| United States. Court of Claims, Audrey Bernhardt - 1962 - 712 pages
...decision of the Secretary or his duly authorized representative for the hearing of such appeals shall be final and conclusive : Provided, That if no such...proceeding under this clause, the Contractor shall be 605 Findings of Fart afforded an opportunity to be heard and to offer evidence in support of its appeal.... | |
| United States. Court of Claims, Audrey Bernhardt - 1962 - 964 pages
...contracting officer, or a board as his authorized representative to determine appeals under this article. In connection with any appeal proceeding under this...contractor shall be afforded an opportunity to be heard and offer evidence in support of nis appeal. Pending final decision of a dispute hereunder the... | |
| United States. Court of Claims, Audrey Bernhardt - 1941 - 966 pages
...determine appeals under this clause. In connection with any appeal pro394 Opinion of the Court ceeding under this clause, the contractor shall be afforded an opportunity to be heard and offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the... | |
| United States. Congress. House. Committee on Armed Services - 1960 - 1930 pages
...appeal prrx-eeding under this clause, the Contractor shall be afforded an opportunity to tie heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereumler, the Contractor shall proceed diligently with the performance of the contract and in accordance... | |
| United States. Marine Corps - 1949 - 862 pages
...foregoing, except where sales are made at retail to the general public on a fixed price basis. 25. DISPUTES. Except as otherwise provided in this contract,...Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with the... | |
| United States. Marine Corps - 1949 - 854 pages
...decision of the Secretary or his duly authorized representatve for the hearing of such appeals shall be final and conclusive : Provided, that if no such...Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with the... | |
| 1955 - 1316 pages
...Imply bad faith, or not supported by substantial evidence, be final and conclusive; provided that, II no such appeal Is taken, the decision of the Contracting...Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with the... | |
| 1960 - 674 pages
...30 days, the decision of the Commanding General ( •) or that of his duly authorized representative shall be final and conclusive. In connection with...Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with Contracting... | |
| 1999 - 574 pages
...so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence. ID connection with any appeal proceeding under this clause,...Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with the... | |
| |