| United States. Court of Claims, Audrey Bernhardt - 1968 - 922 pages
...by the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action,...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| 1977 - 1240 pages
...receipt by the Contractor of the notification of change; Provided, however. That the Contracting Officer, If he decides that the facts justify such action,...(c) below, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. (c) Notwithstanding the provisions of paragraphs... | |
| 1974 - 686 pages
...receipt by the contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action,..."Disputes". However, except as provided in paragraph (c) of this section, nothing in this clause shall excuse the contractor from proceeding with the contract... | |
| 1978 - 188 pages
...receipt by the contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action,..."Disputes". However, except as provided in paragraph (c) of this section, nothing in this clause shall excuse the contractor from proceeding with the contract... | |
| 1983 - 782 pages
...receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action,...clause of this contract entitled "Disputes." However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. ยง... | |
| 1969 - 752 pages
...decides that the facts justify such action, may receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure...(c) below, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. (c) Notwithstanding the provisions of paragraphs... | |
| 1974 - 918 pages
...facts justify such action, may receive and act upon any such claim asserted at any time prior to flnal payment under this contract. Failure to agree to any...(c) below, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. (c) Notwithstanding the provisions of paragraphs... | |
| 1967 - 694 pages
...receipt by the Contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action,...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| 1981 - 706 pages
...Contracting Officer, if he decides that the facts justify such action, may receive and act upon any claim asserted at any time prior to final payment...clause of this contract entitled "Disputes". However, nothing in this clause shall excuse the Contractor from proceeding with the contract as modified. (b)(1)... | |
| 1982 - 1316 pages
...of the notification of change; provided, however, thai the Contracting Officer, if he decides thai the facts justify such action, may receive and act...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| |