| United States. Court of Claims, Audrey Bernhardt - 1968 - 922 pages
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." However, nothing... | |
| 1967 - 2356 pages
...sureties. If any, make changes In or additions to specifications, Issue additional Instructions, required modified or additional work or services within the..."Disputes" clause of this contract. However, nothing hi this clause shall excuse the Contractor from proceeding with the contract as changed. § 7.1201-16... | |
| 1972 - 186 pages
...sureties, if any, make changes In or additions to specifications, issue additional Instructions, required modified or additional work or services within the...to any adjustment shall be a dispute concerning a question of fact within the meaning oí the "Disputes" clause or this contract. However, nothing In... | |
| 1978 - 944 pages
...this contract, an equitable adjustment shall be made in the estimated cost, the completion schedule, or both, and the contract shall be modified in writing...contract. Failure to agree to any adjustment shall be • dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract.... | |
| 1979 - 1186 pages
...to be paid to the Contractor; and (iii) in such other provisions of the contract as may be affected, contract shall be modified in writing accordingly....prior to final payment under this contract Failure to 7-404.1 ARMED SERVICES PROCUREMENT REGULATION 7:267 CONTRACT CLAUSES AND SOLICITATION PROVISIONS agree... | |
| 1983 - 780 pages
...of performance, or both, and (ii) in such provisions of the contract as may be so affected, and the contract shall be modified in writing accordingly....any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| 1983 - 1104 pages
...the Contractor for adjustment under this clause must be asserted within sixty (60) days from the dale of receipt by the Contractor of the notification of...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." However, nothing... | |
| 1965 - 670 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within (60) days from the date of receipt by the Contractor of the...final payment under this contract. Failure to agree at any adjustment shall be a dispute concerning a question of fact within the meaning of the clause... | |
| 1964 - 432 pages
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| 1978 - 188 pages
...of receipt by the Contractor of the notification Title 41 — Public Contracts, Property Management of change: Provided, however, that the Contracting...to any adjustment shall be a dispute concerning a question of fact v.'ithin the meaning of the clause of this contract entitled "Disputes". However,... | |
| |