| 2005 - 692 pages
...the whole or any part of a job order if the Contractor fails to — 48 CFR Ch. 2 (10-1-05 Edition) (1) Make delivery of the supplies or to perform the...caused by the default of a subcontractor, and if such defau1t arises out of causes beyond the control of both the Contractor and subcontractor, and without... | |
| 1997 - 772 pages
...of default to the Contractor, terminate the whole or any part of a Job order If the Contractor falls to — (1) Make delivery of the supplies or to perform...strikes, freight embargoes, and unusually severe weather. Department of Defense (c) If the Contractor's failure to perform is caused by the default of a subcontractor,... | |
| 1999 - 764 pages
...order arises from causes beyond the control and fithout the fault or negligence of the Con•ractor. Examples of such causes include acts of God or of...restrictions, strikes, freight embargoes, and unusually severe *eather. <c) If the Contractor's failure to perform is caused by the default of a subcontractor, and... | |
| 1983 - 716 pages
...the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government...strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond the control and without the fault or negligence... | |
| 1985 - 592 pages
...fault or negligence of the Contractor. (b) Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government...strikes, freight embargoes, and unusually severe weather, but in every case the failure to perform must be beyond the control and without the fault or negligence... | |
| 1968 - 1348 pages
...fault or negligence of the Contractor. Such causes may Include, but are not restricted to. acts of Ood or of the public enemy, acts of the Government In...strikes, freight embargoes, and unusually severe weather; but In every case the failure to perform must be beyond the control and without the fault cr negligence... | |
| 1973 - 968 pages
...18-8.709 negligence oí the Contractor. Such causes may Include, but are not restricted to: Acte of Qod or of the public enemy, acts of the Government In...strikes, freight embargoes, and unusually severe weather, but In every case the failure to perform must be beyond the control and without the fault or negligence... | |
| 1998 - 766 pages
...causes beyond the control and without the fault or negligence of the Contractor. Examples of such causee include acts of God or of the public enemy, acts of...fires. floods, epidemics, quarantine restrictions, strike*, freight embargoes, and unusually severe weather. 252.217-7010 (c) If the Contractor's failure... | |
| 1966 - 1420 pages
...fault of negligence of the Architect-Engineer. Such causes may Include but are not restricted to: acts of God or of the public enemy; acts of the Government...floods; epidemics; quarantine restrictions; strikes; and unusually severe weather; but in every case, the failure to perform must be beyond the control... | |
| 1975 - 1236 pages
...fault or negligence of the Architect-Engineer. Such causes may include but are not restricted to: acts of God or of the public enemy; acts of the Government...floods; epidemics; quarantine restrictions; strikes; and unusually severe weather, but in every case, the failure to perform must be beyond the control... | |
| |