...final and conclusive on the parties hereto, subject only to appeal, within 30 days, by the contractor to the head of the department concerned or his duly authorized representative: whose decision on such appeal us to the facts of delay and the extension of time for completing the work shall be... | |
| United States. General Accounting Office - 1929 - 804 pages
...to the facts of delay shall be final and conclusive on the parties hereto. ARTICLE 15. Disputes. — Except as otherwise specifically provided in this...contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor within thirty days... | |
| United States. Bureau of Reclamation - 1930 - 132 pages
...extend to this contract if made with a corporation for its general benefit. ARTICLE 15. Disputes. — Except as otherwise specifically provided in this...contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor within thirty days... | |
| United States. Department of the Interior, Ray Lyman Wilbur, Elwood Mead - 1933 - 338 pages
...extend to this contract if made with a corporation for its general benefit. ART. 15. Disputes. — Except as otherwise specifically provided in this...contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor within thirty days... | |
| United States. Army. Corps of Engineers - 1934 - 396 pages
...extend to this contract if made with a corporation for its general benefit. Article 14. Disputes. — Except as otherwise specifically provided in this...arising under this contract shall be decided by the Deputy Contracting 0fficer subject to written appeal by the Contractor within 30 days to the Chief... | |
| 1950 - 1346 pages
...to extend to this contract if made with a corporation for its general benefit. ARTICLE 9— DISPUTES Except as otherwise specifically provided in this...Contracting Officer, subject to written appeal by the City within 30 days to the Secretary of the Navy or his duly authorized representative, whose decision... | |
| 1939 - 1554 pages
...in connection with the development of projects where contract provisions state substantially that: "All disputes concerning questions of fact arising...shall be decided by the contracting officer subject to appeal by the contractor within 30 days to the head of the department concerned or his duly authorized... | |
| 1939 - 1306 pages
...$20,000 may (at the option of the contractor), contain the following article without deviation: Disputes. Except as otherwise specifically provided in this...contract, all disputes concerning questions of fact which may arise under this contract, and which are not disposed of by mutual agreement, shall be decided... | |
| 1939 - 1054 pages
...conclusive on the parties to the contract, subject only to appeal, within 30 days, by the contractor to the head of the department concerned, or his duly authorized representative? in connection with contracts on Standard Form No. 32, whose decision on such appeal as to the facts... | |
| United States. Bureau of Yards and Docks, William Martin Smith - 1940 - 58 pages
...excepted by the Contractors from the operation of the release. DISPUTES ARTICLE 15. Except as may be otherwise specifically provided in this contract,...Contracting Officer subject to written appeal by the Contractors within 30 days to the Secretary of the Navy or his duly authorized representative, whose... | |
| |