" The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor... "
Cases Decided in the Court of Claims of the United States - Page 244
by United States. Court of Claims - 1948
Full view - About this book

The Code of Federal Regulations of the United States of America

1971 - 844 pages
...performance of the work shall not be terminated for default because of any delays In the completion of work due to unforeseeable causes beyond the control and...the contractor, including, but not •restricted to, acts of God, or the public enemy, acts of the Government in either its sovereign or contractual capacity,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1965 - 700 pages
...performance of the work shall not be terminated for default because of any delays in the completion of work due to unforeseeable causes beyond the control and...the Contractor, Including, but not restricted to, acts of God, or of the public enemy, acts the Government In either its sovereign or contractual capacity,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1972 - 928 pages
...performance of the work shall not be terminated for delault because of any delays In the completion of work due to unforeseeable causes beyond the control and...the contractor. Including, but not restricted to, acts of God, or the public enemy, acts of the Government in either Its sovereign or contractual capacity,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1960 - 1448 pages
...actual damages, as provided In paragraph (b) hereof because of any delays in the completion of the work due to unforeseeable causes beyond the control and...the Contractor, Including, but not restricted to, acts of God, or of the public enemy, acts of the United States Government, in either its sovereign...
Full view - About this book

Decisions of the Department of the Interior, Volume 66

United States. Department of the Interior - 1960 - 540 pages
...was not to be charged with liquidated damages because of "any delays in the completion of the work due to unforeseeable causes beyond the control and...of the Contractor," including but not restricted to certain named categories, or because of "delays of subcontractors or suppliers due to such causes."...
Full view - About this book

The Code of Federal Regulations of the United States of America

1966 - 642 pages
...performance of the work shall not be terminated for default because of any delays in the completion of work due to unforeseeable causes beyond the control and...the Contractor, including, but not restricted to, acts of Ood, or of the public enemy, acts the Government in either its sovereign or contractual capacity,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1964 - 762 pages
...performance of the work shall not be terminated for default because of any delays 1-n the completion of work due to unforeseeable causes beyond the control and...the Contractor, Including, but not restricted to, acts of God, or of the public enemy, acts the Government In either Its sovereign or contractual capacity,...
Full view - About this book

Decisions of the United States Department of the Interior, Volume 71

United States. Department of the Interior - 1964 - 710 pages
...not be charged with liquidated damages because of any delays in the completion of the work : * * * due to unforeseeable causes beyond the control and...the contractor, including, but not restricted to, * * * floods » * ». Appellant's argument is, in substance, that the occurrence of a flood, ipso facto,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1955 - 606 pages
...proceed shall not be terminated under this clause because of any delays to the completion of the work due to unforeseeable causes beyond the control and...of the Contractor, including, but not restricted to acts of God, or of the public enemy, acts of the Government (1ncluding, but not restricted to any preference,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1949 - 352 pages
...contractor shall not be charged with liquidated damages or any excess cost when the delay in delivery la due to unforeseeable causes beyond the control and...the contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...