" Contractor charged with liquidated or actual damages, as provided in paragraph (b) hereof because of any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including,... "
Decisions of the Comptroller General of the United States - Page 533
by United States. General Accounting Office - 1929
Full view - About this book

The Code of Federal Regulations of the United States of America

1962 - 596 pages
...Contractor charged with resulting damage if: (1) The delay in the completion of the work arises from unforeseeable causes beyond the control and without...Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the Government in either its sovereign or contractual capacity, acts...
Full view - About this book

The Urban Homesteading Catalogue, Volume 1

Urban Systems Research & Engineering, United States. Department of Housing and Urban Development. Office of Policy Development and Research - 1977 - 284 pages
...this contract at the time of the execution of the contract which are beyond the control and without the fault or negligence of the Contractor, including,...restricted to, acts of God or of the public enemy, acts of another contractor in the performance of some other contract with the Owner, fires, floods, epidemics,...
Full view - About this book

Federal Insurance Act of 1977: Hearings Before the Committee on Banking ...

United States. Congress. Senate. Committee on Banking, Housing, and Urban Affairs - 1977 - 820 pages
...the control and without the fault or negligence of the Contractor. Such cau&M may include, but are not restricted to, acts of God or of- the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions,...
Full view - About this book

1978 NASA Authorization: Hearings Before the Subcommittee on Space Science ...

United States. Congress. House. Committee on Science and Technology. Subcommittee on Space Science and Applications, United States. Congress. House. Committee on Science and Technology. Subcommittee on Aviation and Transportation R. & D. - 1977 - 790 pages
...beyond the control and without fault or negligence of the Contractor. Such causes may include, but are not restricted to. Acts of God or of the public enemy, acts of the Government in either Its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions,...
Full view - About this book

Reclamation Manual, Volume 19

United States. Bureau of Reclamation - 368 pages
...in the open market or under other contracts when the delay of the contractor in making deliveries is due to unforeseeable causes beyond the control and...restricted to, acts of God or of the public enemy, acts or the Government, fires, Hoods, epidemic*, quarantine restrictions, strikes, freight embargoes, unusually...
Full view - About this book

Consumer Product Safety Commission--oversight: Hearings Before the ...

United States. Congress. House. Committee on Interstate and Foreign Commerce. Subcommittee on Oversight and Investigations - 1977 - 1316 pages
...occasioned thereby: Provided, That the contractor shaAl not be charged for any excess costs occasioned by unforeseeable causes beyond the control and without...contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes,...
Full view - About this book

Consumer Product Safety Commission--oversight: Hearings Before the ...

United States. Congress. House. Committee on Interstate and Foreign Commerce. Subcommittee on Oversight and Investigations - 1977 - 954 pages
...excess costs occasioned by unforeseeable causes beyond the control and without the fault or neqligonce of the contractor, including, but not restricted to, acts of God or the public enemy, acts of the Govemrrent, fires, floods, epidsnics, quarantine restrictions, strikes,...
Full view - About this book

Department of Defense appropriations for 1980: hearings before a ..., Part 4

United States. Congress. House. Committee on Appropriations. Subcommittee on Department of Defense - 1979 - 1208 pages
...negligence of the contractor . . ." are termed, "Excusable delays." These include, and are not limited to ". . . acts of God or of the public enemy, acts of the government in either its sovereign or contractual capacity, fires, floods . . .," etc. After spacecraft orbital...
Full view - About this book

Telecommunications, Command and Control Programs

U.S. Congress. House. Committee on Appropriations, United States. Congress. House. Committee on Appropriations. Subcommittee on Department of Defense - 1979 - 1200 pages
...negligence of the contractor . . ." are termed, "Excusable delays." These include, and are not limited to ". . . acts of God or of the public enemy, acts of the government in either its sovereign or contractual capacity, fires, floods . . .," etc. After spacecraft orbital...
Full view - About this book

Department of Defense Appropriations for ..., Part 6

United States. Congress. House. Committee on Appropriations - 1979 - 1216 pages
...negligence of the contractor . . ." are termed, "Excusable delays." These include, and are not limited to ". . . acts of God or of the public enemy, acts of the government in either its sovereign or contractual capacity, fires, floods . . .," etc. After spacecraft orbital...