" Contractor, including, but not restricted to, acts of God or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the Gofernment, fires, floods,... "
Department of Agriculture: Appropriations for 1962: Hearings Before the ... - Page 280
by United States. Congress. House. Committee on Appropriations - 1961
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 29

United States. General Accounting Office - 1950 - 710 pages
...of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions,...unusually severe weather or delays of subcontractors due to such causes, if the contractor shall within 10 days from the beginning of any such delay (unless...
Full view - About this book

The Law of Government Contracts

Robert Preston Shealey - 1927 - 600 pages
...beyond the control of and without the fault or negligence of the contractor, and including acts of God, quarantine restrictions, strikes, freight embargoes,...unusually severe weather or delays of subcontractors, within which to apply in writing to the contracting officer for extension of time for completing the...
Full view - About this book

Hearings Before the Committee on the Judiciary, House of Representatives ...

United States. Congress. House. Committee on the Judiciary - 1928 - 900 pages
...contractor, including, but not restricted, to, acts of God or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...unusually severe weather or delays of subcontractors due to such causes." For the entire provision relating to delays and damages see section 9 of Standard...
Full view - About this book

Treasury Department Appropriation Bill for 1929: Hearing Before the ...

United States. Congress. House. Committee on Appropriations - 1928 - 970 pages
...contractor, including, "but not restricted to. acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...unusually severe weather or delays of subcontractors due to such causes: Provided, That the contractor shall within ten days from the beginning of any such...
Full view - About this book

To Establish Uniform Requirements for Government Contracts: Hearing Before ...

United States. Congress. House. Committee on the Judiciary - 1928 - 228 pages
...contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...embargoes, and unusually severe weather, or delays of the subcontractors due to such causes." This provision is made known to all bidders and it is assumed,...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 8

United States. General Accounting Office - 1929 - 804 pages
...occurrence of said delays. It may be stated, however, in this connection that the contract requirement that the contractor shall within 10 days from the beginning of any delay notify the contracting officer in writing of the cause of delay, is a condition precedent to...
Full view - About this book

Quarters and Allowances at St. Elizabeths Hospital: Hearings, Seventieth ...

United States. Congress. House. Committee on Expenditures in the Executive Departments - 1929 - 266 pages
...interruptions to transportation, or shortage of rail or water transportation equipment; (6) Provided further, That the contractor shall within 10 days from the beginning of any delay notify the contracting officer in writing as to the cause of delay, who shall ascertain the facts...
Full view - About this book

Quarters and Allowances at St. Elizabeths Hospital: Hearings Before the ...

United States. Congress. House. Committee on Expenditures in the Executive Departments - 1929 - 252 pages
...interruptions to transportation, or shortage of rail or water transportation equipment; (b) Provided further, That the contractor shall within 10 days from the beginning of any delay notify the contracting officer in writing as to the cause of delay, who shall ascertain the facts...
Full view - About this book

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - 1930 - 132 pages
...contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...unusually severe weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within ten days from the beginning...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 9

United States. General Accounting Office - 1930 - 608 pages
...contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions,...strikes, freight embargoes, and unusually severe weather, but not including delays caused by subcontractors: Provided furthei; That the contractor shall, within...