...grants a further period of time before the date of final payment under the contract. If the parties fall to agree upon the adjustment to be made, the dispute shall be determined as provided in the "Disputes" clause of this contract; but nothing provided in this clause shall excuse the Architect-Engineer... | |
| United States. Department of the Interior - 1960 - 610 pages
...adjust any such claim asserted before the date of final settlement of the contract. If the parties fall to agree upon the adjustment to be made, the dispute shall be determined as provided in Clause 6 hereof." 'Flora Construction Company, 66 ID 315, 324, IBCA-101 (September 4, 1959). •Of.... | |
| 1967 - 674 pages
...unless the Contracting officer grants a further period of time lief ore the date of final payment under the contract. If the parties fail to agree upon the adjustment to be made, the dispute Hhall be determined as provided In Clause B of these General Provisions: but nothing provided in this... | |
| 1967 - 464 pages
...adjust any such claim asserted before the date of final settlement of the contract. If the parties fall to agree upon the adjustment to be made, the dispute shall be determined as provided in the clause of this contract entitled "Disputes." [26 FJtt. 12450, Dec. 27, 1961, as amended by 27 FR... | |
| 1969 - 770 pages
...claim asserted at any time prior to the date of final settlement of the Contract. If the parties fall to agree upon the adjustment to be made the dispute shall be determined as provided in the article entitled "Disputes." Nothing provided in this clause shall excuse the Contractor from proceeding... | |
| 1960 - 1448 pages
...claim asserted at any time prior to the date of final settlement of the contract. If the parties fall to agree upon the adjustment to be made the dispute shall be determined as provided In the clause of this contract entitled "Disputes." But nothing provided In this clause shall excuse the... | |
| 1966 - 292 pages
...adjustment is made under this clause, the contract shall be modified accordingly. If the parties fall to agree upon the adjustment to be made, the dispute shall be determined as provided in the "Disputes" clause, but nothing provided in this clause shall excuse the Contractor from proceeding... | |
| 1965 - 806 pages
...grants a further period of time before the date of final payment under the contract. If the parties fall to agree upon the adjustment to be made, the dispute shall be determined as provided In the "Disputes" clause of this contract; but nothing provided In this clause shall excuse the Contractor... | |
| 1970 - 796 pages
...grants a further period of time before the date of final payment under the contract. If the parties fall to agree upon the adjustment to be made, the dispute shall be determined as provided In the "Disputes" clause of this contract; but nothing provided in this clause shall excuse the Architect-Engineer... | |
| 1967 - 694 pages
...claim asserted at any time prior to the date .of final settlement of the Contract. If the parties fall to agree upon the adjustment to be made the dispute shall be determined as provided in the article entitled "Disputes." Nothing provided in this clause shall excuse the Contractor from proceeding... | |
| |