| 1962 - 596 pages
...23-203 the Contracting Officer grants a further period of time before the date of final payment under the contract. If the parties fail to agree upon the...adjustment to be made, the dispute shall be determined at provided in Clause 6 of these General Provision!. 5. TERMINATION FOR DEFAULT— DAMAGES FOR DELAY—... | |
| United States. Bureau of Reclamation - 368 pages
...duly authorized representative, adjust any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to...from proceeding with the contract as changed. ARTICLE Z. Extrat. — Except as otherwise herein provided, no charge for extras will be allowed unless the... | |
| Arghyrios A. Fatouros - 1994 - 560 pages
...unless the Contracting Officer grants a further period of time before the date of final payment under the contract. If the parties fail to agree upon the...made, the dispute shall be determined as provided in Clause 6 of the general provisions,86 but nothing provided in this clause shall excuse the contractor... | |
| United States. Department of the Interior - 1964 - 710 pages
...may receive and consider, and adjust any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to...made the dispute shall be determined as provided In Clause 6 hereof. But nothing provided in this clause shall excuse the Contractor from proceeding with... | |
| 1965 - 700 pages
...may receive and consider, and adjust any such claim asserted at any time prior to the date of final settlement of the Contract. If the parties fail to...made the dispute shall be determined as provided in the article entitled "Disputes." Nothing provided in this clause shall excuse the Contractor from proceeding... | |
| United States. Congress. House. Committee on Appropriations - 1961 - 1288 pages
...determines the facts fa justify, consider and adjust any such claim asserted before the date of final settlement of the contract. If the parties fail to...made, the dispute shall be determined as provided in Clause 6 hereof. F5. TERMINATION FOR DEFAULT— DAMAGES FOR DELAY— TIME EXTENSIONS [(a) If the Contractor... | |
| 1963 - 666 pages
...determines the facts so Justify, consider and adjust any such claim asserted before the date of final settlement of the contract. If the parties fail to...made, the dispute shall be determined as provided in the clause of this contract entitled "Disputes." [26 FR 12450, Dec. 27, 1961, as amended by 27 PR 3387,... | |
| 1960 - 268 pages
...determines the facts so justify, consider and adjust any such claim asserted before the date of final settlement of the contract. If the parties fail to...made, the dispute shall be determined as provided in Clause 6 hereof. 5. TERMINATION FOR DEFAULT— DAMAGES FOR DELAY— TIME EXTENSIONS (a) If the Contractor... | |
| 1964 - 660 pages
...determines the facts so justify, consider and adjust any such claim asserted before the date of final settlement of the contract. If the parties fail to...made, the dispute shall be determined as provided in the clause of this contract entitled "Disputes." [26 PB 12450, Dec. 27, 1961, as amended by 27 PK 3387,... | |
| 1964 - 440 pages
...unless the Contracting Officer grants a further period of time before the date of final payment under the contract. If the parties fail to agree upon the...made, the dispute shall be determined as provided in Clause 6 of these General Provisions; but nothing provided in this clause shall excuse the Contractor... | |
| |